Which aspect does the "Do" part of the PDCA Cycle focus on?

Get ready for the ISO 27001 Internal Auditor Exam. Learn through flashcards and multiple choice questions with hints and explanations. Ace your auditor test!

The "Do" part of the PDCA (Plan-Do-Check-Act) Cycle specifically emphasizes the implementation of plans that were developed during the "Plan" phase. In this phase, the organization puts into action the strategies and processes that have been devised to achieve the specific objectives related to information security management systems.

This aspect is crucial because it is during the "Do" phase that the theoretical plans are transformed into practical actions. This helps in managing, measuring, and analyzing the operational processes to ensure that they align with the objectives set out in the planning phase. Effectively implementing these plans also involves training personnel, applying resources, and using appropriate tools, all of which contribute to achieving the intended outcomes of the information security framework.

While assessing risks, evaluating results, and documenting policies are important aspects of an organization's overall framework in managing information security, they pertain to different phases of the PDCA Cycle. The assessment of risks occurs during the planning phase, the evaluation of results happens in the checking phase, and policy documentation is generally part of the planning and check phases. Thus, the primary focus during the "Do" stage is solely on the execution of previously established plans.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy